SCH Number 2009068314
Project Info
- Title
- Lift Station 2 and 2A
- Description
- The existing wet well and associated piping in the existing control building (currently referred to as Lift Station 2) will be abandoned. Upon completion of the Project, all flow will be pumped through the three wet wells outside the control building (currently referred to as Lift Station 2A, which will be renamed Lift Station 2 upon completion of the Project). Control building modifications include: removing the existing emergency generator, partition wall, and hoist rail; installing ventilation, flooring, and floor drains; repairing wall defects and damage to the roof directly related to equipment removal and reconfiguration associated with the Project.
2 documents in project