- The Modesto Irrigation District (MID) plans to reconductor the 69-kilovolt (kV) transmission line between the Rosemore and Finney Substation. The project consist of replacing the conductors with new high-ampacity conductors. Along the majority of the project MID will replace the conductors along the existing route and may require replacing some poles. MID proposes to build2.7 miles of new transmission line along MID Lateral Number 4, approximately 1,000 feet to the south of the current alignment along the south side of Maze Boulevard (Highway 132).
3 documents in project
Type | Lead/Public Agency | Received | Title |
---|---|---|---|
NOD | Modesto Irrigation District | Rosemore-Finney 69-kV Transmission Line Reconductoring Project | |