SCH Number 2007012116


Project Info

Title
Apple Computer 69-kV Electric Distribution Project
Description
SMUD proposes to construct and operate a 69-kV subtransmission power line that is required to serve a dedicated substation at Apple Computer, Inc. The proposed overhead subtransmission line would be 1.1-miles-long. It would upgrade an existing 12-kV line. Approximately 0.75 mile of the existing 12-kV line would be upgraded to a 69-kV configuration with a 12-kV underbuild, and ~0.35 mile of the existing 12-kV line would be uprgraded to a new 69-kV line without an underbuild.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
Sacramento Municipal Utility District Apple Computer 69-kV Electric Distribution Project
Sacramento Municipal Utility District Apple Computer 69-kV Electric Distribution Project