SCH Number 2006021057
Project Info
- Title
- Riverdale PUD Arsenic Compliance Project
- Description
- Installation of an arsenic treatment unit rated for 1000-gallons per minute (1.44 MGD) for two existing municipal wells (Riverdale PUD Well Nos. 4 and 5) to meet new Federal arsenic guidelines. The treatment unit will be installed at the Well No. 5 site and Well No. 4 will be connected to the treatment unit via a 2000-ft pipeline.
4 documents in project
Type | Lead/Public Agency | Received | Title |
---|---|---|---|
NOD | Riverdale Public Utility District | Riverdale PUD Arsenic Compliance Project | |
NOD | Riverdale Public Utility District | Riverdale PUD Arsenic Compliance Project | |
NOD | Riverdale Public Utility District | Riverdale PUD Arsenic Compliance Project | |
NEG | Riverdale Public Utility District | Riverdale PUD Arsenic Compliance Project |