- SAA #5-0328-00 Alter the streambed in order to respond to a Restoration Order issued by the County at four locations along Wood Canyon Creek. The four locations where the repair activities occurred are referred to as Dip Crossing 1. East Side Riprap, and Dip Crossing 2. The Corrugated Metal Pipe (CMP) Culvert is a new project addressed under this Agreement. At the Dip Crossing 1 site, the area to be revegetated totals approximately 0.99 acre as revised. At the East Side Riprap site, the area to be revegetated totals approximately 0.30 acre. At the Dip Crosssing 2 site, the area to be revegetated totals approximately 0.09 acre. At the C.M.P. Culvert site, the existing culvert and earthern plug will be removed, and a gabion wall will be constructed.