Don Chapin Sand Dryer Plant
2 Documents in Project
Summary
SCH Number
2025010969
Lead Agency
Merced County
Document Title
Don Chapin Sand Dryer Plant
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
Industrial (I) land use designation and Light Manufacturing (M-1) zoning designation
Document Description
The Don Chapin Sand Dryer Plant Project (project) is the construction and operation of a new sand drying plant and precast concrete manufacturing facility as an addition/expansion to the Don Chapin Ready Mix Concrete Batch Plant located at 23878 Ingomar Grade in the Volta area in Merced County. The project site consists of three parcels with a cumulative acreage of 11.91 located directly adjacent and to the east of 23878 Ingomar Grade on the northeast side of South Ingomar Grade, 960 feet east of South Volta Road in the Volta area, identified as Assessor’s Parcel Numbers (APNs) 081-060-086, -087, and -088.
The project would include the construction and operation of a sand dryer plant and precast concrete manufacturing facility with an operations building, truck scale, and other associated equipment; three (3) storage buildings; and other associated features, including a precast shop office and breakroom, an employee parking area, concrete storage areas, a catch basin, a lined retention basin, and fencing.
The proposed sand dryer plant would be constructed in the western portion of the project site and would encompass a total area of 23,000 square feet. The proposed sand dryer plant would consist of a sand dryer, a load-out belt, a feed ramp, two (2) feed hoppers with a feed belt, product storage bunkers, an operations building, and a truck scale. The proposed sand dryer plant would be equipped with a 75-foot-tall elevator and up to eight (8) storage silos 36 feet tall, and a screening system that is atop the silo system that is an additional 25.5 feet tall making the silo and screen system a total of 61.5 feet tall. The maximum height of the tallest part of the proposed sand dryer plant would be 75 feet. The plant would sort and dry pre-washed sand products into dried sand products for bagging and bulk use in value-added processes. Additionally, the precast concrete manufacturing operation would utilize new and returned concrete from the on-site ready mix plant to manufacture concrete products such as highway barrier rails, septic and other tanks, catch basins, and other associated precast concrete products. The products would be stored on-site and picked up by customers or delivered using facility trucks.
The project would include the construction of three (3) storage buildings for dried materials located in the northwestern portion of the project site, including a 12,000-square-foot storage building for bulk products, a 10,020-square-foot storage building for sacked products, and a 12,000-square-foot storage building for bagged storage. The storage buildings are planned to be constructed in two (2) or three (3) phases. The 12,000-square-foot storage building for bulk products and the 10,020-square-foot storage building for sacked products would be constructed in the first phase or second phase of construction. The 12,000-square-foot storage building for bulk products would be constructed in the second or third phase of construction.
The project includes the construction and installation of other proposed structures and equipment, including a 4,000-square-foot precast shop office and breakroom, a 20,060-square-foot employee parking area, precast concrete storage areas, a catch basin, a lined retention basin, fencing, security lighting, and utility infrastructure. The existing vehicle ingress and egress located at 23878 Ingomar Grade would be maintained and no new points of ingress or egress would be created on the project site.
The project includes the installation of a 4,000-square-foot precast concrete shop office and breakroom in the northern portion of the project site. The precast shop office and breakroom would be used as a breakroom, small office space, and storage for tools.
The project includes the construction of a 20,060-square-foot employee parking area in the southwestern portion of the project site. The parking area would consist of 16 parking stalls and asphalt-concrete paving. The proposed sand dryer plant would be closed to the public and no visitors or customers are expected. Further, ample parking for employees and all visitors exists at the Don Chapin Ready Mix Concrete Batch Plant location and, as a result, no new Americans with Disabilities Act or electric vehicle stalls are required or proposed.
The project includes the construction of a precast tank/catch basin, a pumping system, and a lined storage retention basin with the capacity to capture a 10-year stormwater elevation of 100.45 feet, with a maximum level of 101.5 feet and a total volume of 3.25 acre-feet. The purpose of the retention basin is to catch all stormwater and surface runoff from leaving the project site. The stored and retained water would be returned to the ready mixed concrete batch plant for use in the concrete manufacturing process.
The project includes the installation of 6-foot-tall chain link fencing topped with three (3) strands of barbed wire and equipped with a view guard. The fencing would be installed along the entire perimeter of the project site. A total of ten (10) outdoor lights would be installed for security purposes only, four (4) on the sand dryer plant and a total of six (6) on the operations, breakroom, and storage buildings.
The project would utilize the existing water well located on the Don Chapin Ready Mix Concrete Batch Plant location and no new water well would be required. The project would not require any additional water use for plant operations or employee facilities. Additionally, the project would utilize the existing septic system located on the Don Chapin Ready Mix Concrete Batch Plant location and no new septic system would be required on the project site.
An existing Pacific Gas and Electric Company (PG&E) natural gas line is present along Ingomar Grade and would provide natural gas to the project once connected. In addition, the project is expected to be provided with electricity by a service drop from PG&E, consisting of at least 1,200 amps. It is anticipated that the project would require 9,000,000 British thermal units (Btus) and 600 amps of electrical service. The additional service is being installed for potential future truck charging facilities for electric-powered trucks and equipment. The Don Chapin Ready Mix Concrete Batch Plant location is currently being permitted to install solar power augmentation, which would add solar power to the existing ready mix concrete batch plant and the proposed sand dryer plant. Installation of solar power is not included in the proposed project.
Construction of the project would result in approximately 11.91 acres of ground disturbance, including 5,600 cubic yards of cut and 2,460 cubic yards of fill with 3,200 cubic yards to be balanced or stored on-site. Construction activities are anticipated to begin in early 2025 and would occur over a total estimated timeframe of 36 months, including up to four (4) weeks for grading activities, four (4) weeks for the construction and installation of the proposed drainage basins and underground utilities, 12 to 16 weeks for construction of the sand dryer plant and building foundations, and a phased two-year period for final site construction. Construction activities would be limited to weekdays during daytime hours (7:00 a.m. through 3:30 p.m.). Construction activities would require the use of an aerial lift, a crane, an excavator, a forklift, a grader, two (2) tractors, a paver, a roller, a rubber-tired loader, a scraper, and other similar construction equipment. Construction activities would include four (4) to five (5) construction workers per day. Water for dust control would be used on an as-needed basis depending on the season of construction.
Operation of the sand dryer plant is anticipated to commence in mid-2025 and the operation of other proposed buildings and facilities would commence in 2026 and/or 2027. Operation of the project would result in approximately 30 daily vehicle trips, including 18 truck trips. Truck trips would be required to haul sand and other materials to the sand dryer plant from Los Banos and to haul/ship the finished product. The proposed sand dryer plant would be closed to the public and no visitors or customers are expected. The proposed sand dryer plant and precast concrete operation would operate Monday through Friday between 7:00 a.m. and 5:00 p.m. and would employ six (6) new employees.
The project would result in approximately 50 gallons per day of additional wastewater flows that would be treated by the existing septic system located at the ready mix concrete batching plant. No additional water use for project activities would be necessary. The sand dryer plant would require the use of natural gas and electricity provided by PG&E.
The project proposes to construct and operate a new sand drying plant and precast concrete manufacturing facility as an addition/expansion to the adjacent Ready-Mix Concrete Batch Plant (“Don Chapin Ready Mix Concrete Batch Plant”). The project would include the construction and operation of a sand dryer plant and precast concrete manufacturing facility with an operations building, truck scale, and other associated equipment; three (3) storage buildings; and other associated features, including a precast shop office and breakroom, an employee parking area, concrete storage areas, a catch basin, a lined retention basin, and fencing. The project site is located on northeast side of Ingomar Grade, approximately 948 feet east of Volta Road in the Volta area, identified as Assessor’s Parcel Numbers (APNs) 081-060-086, 081-060-087, and 081-060-088. The project site is designated and Industrial land use in the General Plan and zoned M-1 (Light Manufacturing).
Contact Information
Name
Tiffany Ho
Agency Name
Merced County Community & Economic Development
Job Title
Deputy Director of Planning
Contact Types
Lead/Public Agency
Phone
Name
Jessica Cleavenger
Agency Name
SWCA Environmental Consultants
Job Title
Senior Environmental Planner
Contact Types
Consulting Firm
Phone
Name
Don Chapin
Agency Name
Don Chapin Sand Dryer Co., LLC
Job Title
Owner
Contact Types
Project Applicant
Phone
Email
Location
Coordinates
Cities
Los Banos, Merced
Counties
Merced
Regions
Unincorporated
Cross Streets
Ingomar Grade & Volta Road
Zip
93635
Total Acres
11.91
Jobs
6
Parcel #
081-060-086, 081-060-087, 081-060-088
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Air Resources Board (ARB), California Department of Parks and Recreation, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 10 (DOT), California Department of Transportation, Division of Aeronautics (DOT), California Department of Transportation, Division of Transportation Planning (DOT), California Department of Water Resources (DWR), California Energy Commission, California Fish and Game Commission (CDFGC), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, Central Valley Fresno Region 5 (RWQCB), California State Lands Commission (SLC), Central Valley Flood Protection Board, Delta Protection Commission, Delta Stewardship Council, Office of Historic Preservation, San Francisco Bay Conservation and Development Commission (BCDC), State Water Resources Control Board, Division of Drinking Water, State Water Resources Control Board, Division of Water Quality, State Water Resources Control Board, Division of Water Rights, California Department of Fish and Wildlife, Central Region 4 (CDFW)
State Reviewing Agency Comments
California Department of Fish and Wildlife, Central Region 4 (CDFW)
Development Types
Industrial (Addition/expansion to the Don Chapin Ready Mix Concrete Batch)(Sq. Ft. 23000, Acres 11.91, Employees 6)
Local Actions
Site Plan
Project Issues
Biological Resources, Cultural Resources, Land Use/Planning, Tribal Cultural Resources, Utilities/Service Systems
Public Review Period Start
Public Review Period End
Attachments
Draft Environmental Document [Draft IS, NOI_NOA_Public notices, OPR Summary Form, Appx,]
Notice of Completion [NOC] Transmittal form
State Comment Letters [Comments from State Reviewing Agency(ies)]
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.