Removal Action Workplan: Catalina Two Harbors Water System

Summary

SCH Number
2024070073
Public Agency
California Department of Toxic Substances Control (DTSC)
Document Title
Removal Action Workplan: Catalina Two Harbors Water System
Document Type
NOE - Notice of Exemption
Received
Posted
7/2/2024
Document Description
The project consists of implementing a Removal Action Workplan (RAW) for performing soil removal at approximately 39 locations where Aboveground Decommissioned Pipe segments of varying length were removed from the land surface adjacent to the existing nine-mile Two Harbors Water Supply Pipeline. The RAW identifies excavation and offsite disposal of soils contaminated with polychlorinated biphenyls (PCBs) and polycyclic aromatic hydrocarbons (PAHs).

Contact Information

Name
Jessy Fierro
Agency Name
Department of Toxic Substances Control
Job Title
Project Manager
Contact Types
Lead/Public Agency

Location

Counties
Los Angeles
Regions
Southern California
Other Location Info
Catalina Island
Other Information
9-mile extent of Two Harbors Water Supply Pipeline

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
Section 15330
Reasons for Exemption
1. The project is a minor action designed to prevent, minimize, stabilize, mitigate or eliminate the release or threat of release of hazardous waste or hazardous substances. 2. The project is a removal action that will not exceed $1 million in cost. 3. The project does not involve the on-site use of a hazardous waste incinerator or thermal treatment unit or the relocation of residences or businesses and does not involve the potential release into the air of volatile organic compounds (VOCs) as defined in Health and Safety Code Section 25123. 4. The project will be consistent with applicable state and local environmental permitting requirements. The project will implement actions to comply with SCAQMD Rule 403. 5. The exceptions pursuant to Cal. Code Regs., tit. 14, § 15300.2 have been addressed as follows: - Cumulative Impact. The project will not result in cumulative impacts because it is designed to be a short-term, final remedy that would not lead to a succession of projects of the same type in the same place over time. - Significant Effect. The environmental safeguards and monitoring procedures that are enforceable and made a condition of project approval will prevent unusual circumstances from occurring so that there is no possibility that the project will have a significant effect on the environment. - Scenic Highways. The project will not damage scenic resources, including but not limited to, trees, historic buildings, rock outcroppings, or similar resources, because it is not located within view of a highway officially designated as a state scenic highway. - Hazardous Waste Sites. The project is not located on a site which is included on any list compiled pursuant to Section 65962.5 of the Government Code. - Historical Resources. The project is not expected to cause a substantial adverse change in the significance of a historical resource because none are anticipated.
County Clerk
Los Angeles

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.