P-18 Sewer Trunkline Project (Capital Project # 50424)

2 Documents in Project

Summary

SCH Number
2024051373
Lead Agency
City of Chico
Document Title
P-18 Sewer Trunkline Project (Capital Project # 50424)
Document Type
NOD - Notice of Determination
Received
Posted
7/3/2024
Document Description
The Project would install a sewer trunkline mainly in the unincorporated area outside the southern City limits. The trunkline would service the majority of the Honey Run/Doe Mill Special Planning Area, South Entler Special Planning Area, and commercial and industrial uses in the area, as identified in the Chico 2030 General Plan and the 2013 Sanitary Sewer Master Plan. The proposed trunkline pipe diameter would range from 1.25-2.25 feet, the trench width would be 6-feet-wide, with total easements 40-feet wide. The trunkline would extend approximately 2.85 miles easterly starting from the existing P-17A sewer trunkline located near the intersection of Hegan Lane and the Comanche Creek Greenway bike path. From the connection point, the trunkline would cross Hegan Lane and travel under the Class I bike lane located immediately east of the northbound lane of Midway to Entler Avenue. The trunkline would continue east along Entler Avenue, then continue south along Entler Avenue for approximately 530 feet before crossing underneath SR 99 and extending along the former UPRR right of way for approximately 630 feet. The trunkline then shifts north along a City easement, continues through Cramer Lane and heads east at Morrow Lane. At the eastern terminus of Morrow Lane, the City proposes to install a manhole at the south end of an existing 36-inch culvert and connect a 40 foot long pipe in the existing drainage ditch to provide vehicular construction access to the P-18 Sewer Trunkline Project, and to facilitate future maintenance access to the easterly manholes located on the south side of Skyway. The Project would continue along the southside of Skyway just past the Potter Road intersection and terminate 191 feet east of a manhole on the south side of Skyway.

Contact Information

Name
Tracy R. Bettencourt
Agency Name
City of Chico
Job Title
Senior Planner
Contact Types
Lead/Public Agency / Project Applicant

Location

Cities
Chico
Counties
Butte
Regions
Citywide
Other Information
The Project is located in the southern portion of the City of Chico, California, starting in the west and running easterly, latitude 39.703923, longitude -121.788938. See attached map for a detailed project location.

Notice of Determination

Approving Agency
City of Chico
Approving Agency Role
Lead Agency
Approved On
County Clerk
Butte
Final Environmental Document Available at
https://chico.ca.us/Departments/Engineering/Capital-Projects/P-18-Sewer-Trunkline/index.html

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Final Document(s) [Approved_Certified draft environmental documents]

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print