Inland Feeder-Foothill Pump Station Intertie Project

2 Documents in Project

Summary

SCH Number
2024050868
Lead Agency
Metropolitan Water District of Southern California
Document Title
Inland Feeder-Foothill Pump Station Intertie Project
Document Type
NOD - Notice of Determination
Received
Posted
8/21/2024
Document Description
The proposed Project consists of the installation of two new pipeline connections between the Inland Feeder and the San Bernardino Valley Municipal Water District-Inland Feeder Interconnection Line 1 and Foothill Pump Station. Both new pipelines would have their own valves, valve vault structures, and surge tanks. Additionally, a vault structure with valve will be installed on the Inland Feeder to control direction of water flow along Inland Feeder. The two pipelines are referred to as the supply connection and the discharge connection. The supply connection pipeline would be approximately 500 feet in length and send water from the Inland Feeder to the Foothill Pump Station for pumping. The discharge connection pipeline would be approximately 1,000 feet in length and send the pumped water back into the Inland Feeder, allowing it to have enough pressure flow to its final destination of the Rialto Pipeline. Both the supply and discharge pipelines would be approximately 54 inches in diameter. Construction staging and storage would occur on the open dirt and gravel space within Metropolitan’s fee property in the Project Area. Operations and maintenance activities at the Inland Feeder and Foothill Pump Station, including the frequency of staff visits, maintenance, and shutdowns, would be similar to existing conditions once construction activities are completed.

Contact Information

Name
Michelle Morrison
Agency Name
Metropolitan Water District of Southern California
Job Title
Senior Environmental Specialist
Contact Types
Lead/Public Agency

Location

Cities
Highland
Counties
San Bernardino
Regions
Southern California
Cross Streets
Greenspot Road and Cone Camp Road
Zip
92346
Total Acres
10
Parcel #
121038125; 121038124; 029115102
State Highways
NA
Railways
NA
Airports
Redlands Municipal Airport
Schools
Cram Elementary; Arroyo Verde Elementary
Waterways
Santa Ana River; Plunge Creek
Township
T1S
Range
R3W
Section
1
Base
Redlands

Notice of Determination

Approving Agency
Metropolitan Water District of Southern California
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Bernardino
Final Environmental Document Available at
700 N. Alameda Street, Los Angeles, CA 90012

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print