Reestablish Drainage West Side DEPP Sump

Summary

SCH Number
2024020830
Public Agency
California Department of Water Resources (DWR)
Document Title
Reestablish Drainage West Side DEPP Sump
Document Type
NOE - Notice of Exemption
Received
Posted
2/22/2024
Document Description
San Joaquin field division plans to reestablish a drainage ditch, reestablish a berm, remove sediment from a sump, and regrade and add gravel to a road that was washed out. To reestablish the drainage ditch, a one-foot-deep by 230-foot-long v-ditch along the Berrenda Mesa fence line would be dug out using either a grader or backhoe. Sediment would be loaded onto a dump truck and taken to the Devil’s Den Pumping Plant (DEPP) spoil pile site. To reestablish the berm, an excavator and bulldozer would be used to scrape sediment along the sides of the DEPP sump, and then pile the sediment between the sump’s southwest side and the graveled road. The berm would be around 2 feet high and 180 feet long. If more dirt is needed, dirt from the DEPP spoil pile site would be loaded onto a truck and transported to the site. To remove sediment from the sump, the bulldozer and excavator would be used again to clean up the upper shelf of the sump. Water in the lower portion of the sump would be pumped out and into the California aqueduct. The excavator would then be used to remove excess sediment from the lower portion. Lastly, the road between the v-ditch and berm would be regraded with a grader and several inches of gravel would be brought in via a dump truck. The gravel would be spread out and compacted into the road. A service truck would be used to refuel equipment when needed. Equipment staging would take place at DEPP. All work would take place within the DWR right or way. This work is necessary to maintain the sump and to avoid runoff sediment from entering the sump. The work is estimated to take 3-4 weeks to complete. Work is planned for March. However, due to a forecasted wet spring, the work may be postponed until April or May.

Contact Information

Name
Elizabeth Maldonado
Agency Name
Department of Water Resources, San Joaquin Field Division
Job Title
Environmental Scientist
Contact Types
Lead/Public Agency

Location

Cities
Lost Hills
Counties
Kern
Regions
Unincorporated
Other Location Info
The Devil's Den Pumping Plant (DEPP) sump is located at 35°42'34.5"N 120°00'35.4"W. DEPP is located at 35°42'43.3"N 120°00'41.3"W. The DEPP spoil pile site is located at 35°42'45.1"N 120°00'31.9"W.

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
15301 (b)
Reasons for Exemption
This project consists of maintenance activities that support the function of the California Aqueduct and water delivery within the State Water Project.

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print