Cambrian Tanks Replacement Project

2 Documents in Project

Summary

SCH Number
2024010140
Lead Agency
City of San Jose
Document Title
Cambrian Tanks Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
4/17/2024
Document Description
The project would involve demolition of the two existing earthen reservoirs within the project site and construction of two eight-million-gallon pre-stressed concrete tanks within the approximate footprints of the existing tanks. The two existing earthen reservoirs have a combined capacity of 16 million gallons, and the two proposed pre-stressed concrete tanks would have the same combined capacity. Additional supporting infrastructure would also be constructed. The project also includes a lot line adjustment to combine the two parcels.

Contact Information

Name
Cort Hitchens
Agency Name
City of San José
Job Title
Planner III
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Regions
Northern California, San Francisco Bay Area
Cross Streets
3033 South Bascom Avenue
Zip
95124
Total Acres
5.8
Parcel #
414-03-010 and 414-03-11
State Highways
SR 17, SR 85
Railways
Valley Transportation Authority
Airports
N/A
Schools
ABC Preschool, Edison Montessori, Camden Post-Secondary, etc.
Waterways
Los Gatos Creek
Township
8S
Range
1W
Section
2
Base
MtDiablo

Notice of Determination

Approving Agency
City of San José
Approving Agency Role
Lead Agency
Approved On
County Clerk
Santa Clara
Final Environmental Document Available at
https://www.sanjoseca.gov/your-government/departments-offices/planning-building-code-enforcement/planning-division/environmental-review/environmental-review-documents/cambrian-tanks-replacement-project

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print