Chiquito Battery Energy Storage Facility Project

2 Documents in Project

Summary

SCH Number
2023100095
Lead Agency
City of Wildomar
Document Title
Chiquito Battery Energy Storage Facility Project
Document Type
NOD - Notice of Determination
Received
Posted
1/25/2024
Document Description
The project proposes to construct a new 80-megawatt (MW) Battery Energy Storage System (BESS) project, which would be capable of meeting a 4-hour duration, on a vacant lot located north of the intersection of Clinton Keith Road and Grand Avenue. The project proposes to interconnect to the existing Southern California Edison (SCE) 115 kilovolt (kV) Tenaja Substation located directly to the south. The proposed project would store and deliver electricity to the grid through a Generator Interconnection Agreement with SCE.

Contact Information

Name
Matthew Bassi
Agency Name
City of Wildomar
Job Title
Community Development Director
Contact Types
Lead/Public Agency

Location

Cities
Wildomar
Counties
Riverside
Regions
Southern California
Cross Streets
Clinton Keith Road and Grand Avenue
Zip
92595
Total Acres
2.83
Parcel #
380-150-019 and -020
Railways
N/A
Airports
N/A
Schools
Sycamore Academy Charter, Murrieta Spring Adventist Christian Ac
Waterways
Riverine, Murrieta Creek

Notice of Determination

Approving Agency
Planning Commission of the City of Wildomar
Approving Agency Role
Lead Agency
Approved On
County Clerk
Riverside
Final Environmental Document Available at
http://www.cityofwildomar.org/business/important_documents/planning_department_environmental_documents_center/city_adopted_mnds_and_certified_eir_documents

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print