Corporation Yard Project

2 Documents in Project

Summary

SCH Number
2023090193
Lead Agency
Sacramento Area Flood Control Agency
Document Title
Corporation Yard Project
Document Type
NOD - Notice of Determination
Received
Posted
1/29/2024
Document Description
The Corporation Yard Project (proposed project) would include construction of a 6,000 square foot Corporation Yard building on top of the existing CAMU as well as site improvements to help manage the capture and conveyance of storm water collected at the project site. The Corporation Yard building would be used to house RD 537 equipment and office space for levee and drainage maintenance activities. Project site improvements include construction of an access ramp, concrete curb around the top deck of the project site, drop inlets and down chutes to help with stormwater conveyance, and excavation throughout the existing drainage channel to help with the conveyance of stormwater flows. Additionally, SAFCA would install a culvert along the new access ramp to facilitate conveyance of stormwater and would construct a land bridge at the southwest corner of the project site to connect the project site top deck to the existing RD 537 levee.

Contact Information

Name
Dan Tibbitts
Agency Name
SAFCA
Job Title
Project Manager
Contact Types
Lead/Public Agency

Location

Counties
Yolo
Regions
Northern California
Cross Streets
County Road 124 and County Road 126
State Highways
I-5 and I-80
Airports
Sacramento International
Waterways
Sacramento River

Notice of Determination

Approving Agency
Sacramento Area Flood Control Agency
Approving Agency Role
Lead Agency
Approved On
County Clerk
Yolo
Final Environmental Document Available at
1325 J Street, Suite 1700 Sacramento, CA 95814

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.