El Rio Substation Project

2 Documents in Project

Summary

SCH Number
2023090056
Lead Agency
Sacramento Municipal Utility District
Document Title
El Rio Substation Project
Document Type
MND - Mitigated Negative Declaration
Received
Document Description
SMUD is proposing the construction and operation of a new substation and decommissioning and removal of outdated equipment at the existing Elverta Substation. The proposed El Rio Substation would include new transformers and circuit breakers, a control building, paved access, fencing, lighting, stormwater drainage, stormwater retention basin, and utilities. North of the substation, two existing electrical towers carrying 230-kilovolt (kV) transmission lines would be replaced with two or three steel monopoles (also known as steel tubular poles) to tie the substation into the existing grid. Following the energization of the proposed El Rio Substation, the existing Elverta Substation would be decommissioned, and the outdated substation equipment dismantled and removed from the site. Project construction is anticipated to begin during the first quarter of 2025 and would be completed by late 2026, involving active construction for approximately 24 months, and 3 months to decommission the Elverta Substation.

Contact Information

Name
Ammon Rice
Agency Name
Sacramento Municipal Utility District (SMUD)
Job Title
Supervisor, Environmental Services
Contact Types
Lead/Public Agency

Location

Cities
Unincorporated area
Regions
Unincorporated
Cross Streets
West Elverta Road and El Rio Avenue
Zip
95626
Parcel #
202-0090-001, 202-0090-024
Schools
Elverta Elementary School
Waterways
Steelhead Creek
Township
10N
Range
5E
Section
18, 19

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
California Air Resources Board (ARB), California Department of Fish and Wildlife, Bay Delta Region 3 (CDFW), California Department of Fish and Wildlife, North Central Region 2 (CDFW), California Department of Parks and Recreation, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 3 (DOT), California Department of Water Resources (DWR), California Energy Commission, California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Public Utilities Commission (CPUC), Central Valley Flood Protection Board, Office of Historic Preservation, State Water Resources Control Board, Division of Drinking Water, California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB)
State Reviewing Agency Comments
California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB)
Development Types
Other (Electrical Substation)
Local Actions
Redevelopment
Project Issues
Aesthetics, Agriculture and Forestry Resources, Air Quality, Biological Resources, Cultural Resources, Drainage/Absorption, Energy, Geology/Soils, Greenhouse Gas Emissions, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Mineral Resources, Noise, Population/Housing, Public Services, Recreation, Transportation, Tribal Cultural Resources, Utilities/Service Systems, Wildfire
Local Review Period Start
Local Review Period End

Attachments

Notice of Completion [NOC] Transmittal form
State Comment Letters [Comments from state reviewing agencies]

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print