SACRAMENTO COUNTY WATTEV INNOVATIVE FREIGHT TERMINAL (SWIFT) PROJECT

5 Documents in Project

Summary

SCH Number
2023080394
Lead Agency
Sacramento County
Document Title
SACRAMENTO COUNTY WATTEV INNOVATIVE FREIGHT TERMINAL (SWIFT) PROJECT
Document Type
NOD - Notice of Determination
Received
Posted
5/23/2024
Document Description
PLER2023-00069. The project would provide a publicly-accessible Electric Vehicle (EV) charging facility that would be built on a 110-acre parcel of land adjacent to Interstate 5 (I-5 and proximate to State Route 99 (SR-99), both major freight corridors. Facility development would include the installation of Direct Current Fast chargers (DCFC) and Megawatt Chargers powered by a new solar array (solar fields on 96.5 acres) that would support charging for shippers and transporters as well as public transportation and passenger vehicles. The charging areas and associated support facilities would occupy 13.5 acres of land and would be configured with two truck charging areas with trailer parking stalls, separated by a publicly accessible central plaza. The central plaza will include three buildings - one for operations staff, one trucker refreshment/resting lounge, and one convenience store/restroom and visitor center.

Contact Information

Name
Julie Newton
Agency Name
Sacramento County Planning
Job Title
ENVIRONMENTAL COORDINATOR
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Regions
Countywide
Parcel #
225-0010-003, -035, -036, -006

Notice of Determination

Approving Agency
Sacramento County Planning
Approving Agency Role
Lead Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
https://planningdocuments.saccounty.net/

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print