Groundwater Banking Partnership Project

2 Documents in Project

Summary

SCH Number
2023080315
Lead Agency
North Kern Water Storage District
Document Title
Groundwater Banking Partnership Project
Document Type
NOD - Notice of Determination
Received
Posted
10/19/2023
Document Description
The Project includes agreements made between the District and its partners to recharge their water within the District’s existing recharge basins during wet years. These additional recharge volumes would increase the importation of water supplies for groundwater banking, which would be returned to the partners at a later time. Project facilities include 9 high-quality wells, with an average pumping capacity of 5.5 cfs; 8.92 miles of pipeline; one existing well tie-in; and two discharge points to FKC.

Contact Information

Name
David Hampton
Agency Name
North Kern Water Storage District
Job Title
General Manager
Contact Types
Lead/Public Agency

Location

Cities
unincorporated area
Counties
Kern
Regions
Unincorporated
Cross Streets
Burbank Street, Driver Road, McCombs Avenue, and Smith Avenue
Zip
93308
Total Acres
54.06
Parcel #
060-110-46
State Highways
99 and 46
Railways
None
Airports
Shafter-Minter Field
Schools
None
Waterways
Poso Creek, Friant Kern Canal
Township
28S/27
Range
26E/25
Section
20,21
Base
Famoso

Notice of Determination

Approving Agency
North Kern Water Storage District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Kern
Final Environmental Document Available at
https://www.northkernwsd.com/environmental-documents/

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Final Document(s) [Approved_Certified draft environmental documents]

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print