Turtle Bay Boat Ramp Project

4 Documents in Project

Summary

SCH Number
2023020064
Lead Agency
City of Redding
Document Title
Turtle Bay Boat Ramp Project
Document Type
NOD - Notice of Determination
Received
Posted
7/19/2024
Document Description
The project is limited to the improvement and expansion of Turtle Bay Boat Ramp and the surrounding park area, including the widening of the boat ramp, the extension of the floating dock, the construction of a new boating access beach with an Americans with Disabilities Act (ADA)-compliant ramp for drift boats and non-motorized vessel launching, the installation of an ADA-compliant restroom, the extension of the Sacramento River Trail and bike path, and the improvements to stormwater drainage and landscaping. The project, as it pertains to Fish and Game Code section 1602, includes the following activities that either require work within the wetted channel or removal of riparian vegetation: widening of the existing boat ramp, resurfacing of the boat ramp, extension of the existing floating dock, construction of a drift boat and non-motorized boating launch beach, in-water work, and the installation of a temporary fish exclusion and turbidity barrier (gravel berm) which could include the construction of a temporary gravel working pad, and the removal of nine native trees.

Contact Information

Name
Helen Bowman
Agency Name
California Department of Fish and Wildlife
Job Title
Senior Environmental Scientist (Specialist)
Contact Types
Responsible Agency

Location

Cities
Redding
Counties
Shasta
Zip
96001
Parcel #
102-040-015-000
Waterways
Sacramento River
Other Information
Turtle Bay Boat Ramp near 725 Auditorium Drive, Redding, Shasta County, 96001

Notice of Determination

Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Shasta
Final Environmental Document Available at
777 Cypress Avenue, Redding, CA 96001

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.