Santa Margarita 58 CAPM

3 Documents in Project

Summary

SCH Number
2023020025
Lead Agency
California Department of Transportation, District 5 (DOT)
Document Title
Santa Margarita 58 CAPM
Document Type
NOD - Notice of Determination
Received
Posted
4/6/2023
Document Description
The California Department of Transportation (Caltrans) proposes to extend the service life and improve the ride quality of State Route 58 in San Luis Obispo County near the town and census-designated place of Santa Margarita. Caltrans proposes a 0.15-foot Rubberized Hot Mix Asphalt overlay within the project limits (from post mile 1.8 to post mile 6.9). Shoulder backing will be placed along pavement edges. The existing roadway has 11-foot-wide travel lanes with 1-to-2-foot shoulders. The project proposes to widen the roadway with 12-foot lanes near the north side of I Street (post mile 1.8) to West Pozo Road (post mile 3.15). Six-foot shoulders, sidewalks, and curb ramps are proposed from I Street (post mile 1.8) to West Pozo Road (post mile 3.15). Existing asphalt concrete dikes will be upgraded to meet existing standards. Additionally, 10 drainages and 36 roadside sign panels will be replaced, one count station will be installed, and the existing metal beam guardrail will be replaced with the current standard.

Contact Information

Name
Hannah Butler
Agency Name
Caltrans
Job Title
Environmental Scientist
Contact Types
Lead/Public Agency

Location

Counties
San Luis Obispo
Regions
Northern California
State Highways
58

Notice of Determination

Approving Agency
Caltrans
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.