FY 22/23 Gravity Sewer Improvements Project

3 Documents in Project

Summary

SCH Number
2022070130
Lead Agency
Ross Valley Sanitary District
Document Title
FY 22/23 Gravity Sewer Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
9/28/2022
Document Description
The Ross Valley Sanitary District (RVSD) Fiscal Year 2022/2023 Gravity Sewer Improvements Project (#953) (Project) entails the construction and rehabilitation, within the existing alignment, of sanitary sewer mains and related appurtenances within the unincorporated community of Sleepy Hollow, the Town of San Anselmo, the unincorporated communities of Greenbrae and Kentfield, and the City of Larkspur, located within the County of Marin. The Project site encompasses approximately 0.12 acres and the total area disturbed would be approximately 5,403 square ft. The Project would include rehabilitation of sanitary sewer mains in the following area: Sleepy Hollow: Replacing approximately 1,554 linear ft of existing 6-inch (in.) vitrified clay pipe (VCP) with 8-in. high-density polyethylene (HDPE) pipe via pipe bursting methods. No work would occur on the bridge located at Deer Hollow Road. Work would include: • Baltus Lane segment: Removing one existing sanitary sewer cleanout and replacing it with a new sanitary sewer manhole. • Deer Hollow Road segment: Constructing one new manhole in order to pipe burst downstream of the Deer Hollow Bridge, towards Butterfield Road. No work would occur on the bridge, and pipe bursting would continue upstream of the bridge until the end of the segment. Additionally, one existing sanitary sewer cleanout would be removed and replaced with a new sanitary sewer manhole. San Anselmo: Replacing approximately 2,125 linear ft of existing 6-in. VCP with 8-in. HDPE pipe via pipe bursting methods. Additional work would include: • The Alameda segment: Removing five existing sanitary sewer cleanouts and replacing four of the cleanouts with new sanitary sewer manholes. • Greenbrae: Replacing approximately 1,219 linear ft of existing 6-in. VCP with 8-in. HDPE pipe via pipe bursting methods. Kentfield: Replacing approximately 1,575 linear ft of existing 6-in. VCP with 8-in. HDPE pipe via pipe bursting methods. Additional work would include: • Oak Avenue segment: Removing two existing sanitary sewer cleanouts and replacing one of the cleanouts with a new sanitary sewer manhole. • Larkspur: Replacing approximately 120 linear ft of existing 6-in. VCP with 6-in. HDPE pipe via pipe bursting methods. Rehabilitation of all of sanitary sewer mains would occur within the existing alignment. Work would also include the rehabilitation of existing sanitary sewer manholes. Depth of excavation is projected to range from approximately 5 to 12 ft. The primary objective of this Project is to relieve hydraulic and structural deficiencies and reduce groundwater infiltration associated with aging RVSD infrastructure.

Contact Information

Name
Philip Benedetti
Agency Name
Ross Valley Sanitary District
Job Title
Senior Engineer
Contact Types
Lead/Public Agency

Location

Cities
community of Sleepy Hollow, Kentfield, Greenbrae, Larkspur, San Anselmo
Counties
Marin
Regions
Northern California, San Francisco Bay Area, Unincorporated
Cross Streets
See NOC
Zip
See NOC
Total Acres
0.12
State Highways
101, 580
Railways
SMART
Airports
NA
Schools
See NOC
Waterways
See NOC
Other Information
See NOC

Notice of Determination

Approving Agency
Ross Valley Sanitary District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Marin
Final Environmental Document Available at
https://rvsd.org/171/Documents

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Final Document(s) [Approved_Certified draft environmental documents]

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print