Maricopa Highway Capital Maintenance Project (Notification No. EPIMS-KER-35971-R4)
Document Type
NOD - Notice of Determination
Received
Posted
5/4/2023
Document Description
The Project involves activities related to the replacement of existing culvert pipe, and the construction of new concrete headwalls and/or wingwalls at the culvert facilities listed above. Project activities will also include the revegetation of temporarily disturbed areas. Work will be completed when the streams are dry. Project activities may necessitate the Permittee’s acquisition of temporary construction easements for construction and access, night work is not scheduled at this time. The Project will result in approximately 472.5 square feet of permanent impacts in association with the installation of longer culverts compared to existing, and the placement of concrete headwalls and wingwalls. The Project will also result in a total of 7,709 square feet of temporary impacts, in association with Project activities.

Contact Information

Name
Javier Mendez
Agency Name
CDFW
Job Title
Environmental Scientist
Contact Types
Responsible Agency

Name
Ronald Cummings
Agency Name
Caltrans
Job Title
Staff
Contact Types
Lead/Public Agency

Location

Counties
Kern
Regions
Southern California
Other Location Info
In general, the Maricopa Highway Capital Maintenance Project (Project) extends east from the City of Maricopa between post miles 0.0 and 10.2 on State Route (SR)166 within Kern County. The Project involves 8 culverts located near the following SR 166 Post Mile (PM) markers: 2.0, 3.46, 3.96, 6.43, 6.70, 6.79, 6.82, and 10.04. The culvert locations were designated Locations No. 3, No. 5, No. 6, No. 14, No. 15, No. 16, No. 17, and No. 23 by Permittee.

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print