STACK Trade Zone Park

4 Documents in Project

Summary

SCH Number
2022060141
Lead Agency
California Energy Commission
Document Title
STACK Trade Zone Park
Document Type
NOD - Notice of Determination
Received
Posted
5/15/2023
Document Description
STACK Infrastructure (STACK or applicant) filed an application with the CEC seeking an exemption from the CEC’s jurisdiction for the Trade Zone Park (21-SPPE-02). The STACK Trade Zone Park would be located on two parcels of land encompassing approximately 9.8 acres at the corner of Trade Zone Boulevard and Ringwood Avenue (2400 Ringwood Avenue and 1849 Fortune Drive) in the city of San José. STACK Trade Zone Park would include one four-story advanced manufacturing building (approximately 136,573 square feet), two three-story data center buildings (approximately 522,194 square feet), a parking garage, related utility infrastructure, and a 91 MW backup generating facility.

Contact Information

Name
tina garg
Agency Name
City of San Jose
Job Title
Supervising Planner
Contact Types
Responsible Agency

Location

Cities
San Jose
Counties
Santa Clara
Regions
Citywide, San Francisco Bay Area
Cross Streets
Trade Zone Blvd/Ringwood Ave
Zip
95131

Notice of Determination

Approving Agency
City of San Jose
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Santa Clara
Final Environmental Document Available at
https://efiling.energy.ca.gov/Lists/DocketLog.aspx?docketnumber=21-SPPE-02

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Completion [NOC] Transmittal form
Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.