Construction of Maple Wells and Transmission Line

Summary

SCH Number
2022040113
Public Agency
State Water Resources Control Board
Document Title
Construction of Maple Wells and Transmission Line
Document Type
NOE - Notice of Exemption
Received
Posted
4/6/2022
Document Description
The project involved the construction two groundwater wells (Maple Wells 1 and 2) and construction of 700 linear feet of 8-inch diameter ductile iron pipe. The two groundwater wells are located in the City of Beverly Hills' Maple Yard, a city-owned property. Water produce by these wells will be conveyed to the Foothill Water Treatment Plant.

Contact Information

Name
Naira Ghukasyan
Agency Name
State Water Board
Job Title
Environmental Scientist
Contact Types
Lead/Public Agency

Location

Cities
Beverly Hills
Counties
Los Angeles
Regions
Southern California
Other Location Info
345 Foothill Road, Beverly Hills, CA 91210

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
Class 32 Categorical Exemption under CEQA guidelines.
Reasons for Exemption
The location of Maple wells falls on zero priority basin (Hollywood Basin). The project also met the following requirements:(1) The project is consistent with the applicable general plan designation and all applicable general plan policies as well as with applicable zoning designation and regulations. (2) The project occurs within city limits on a project site of no more than five acres substantially surrounded by urban areas. (3) The project site has no value as habitat for endangered, rare or threatened species. (4) The project would not result in any significant effects relating to traffic, noise, air quality, or water quality. (5) The project site can be adequately served by all required utilities and public services. Additionally, the project also complies with State CEQA Section 15300.2 - The project will not cause a substantial adverse change in significance of a historical resource.