North Bayshore Master Plan Project

5 Documents in Project

Summary

SCH Number
2022020712
Lead Agency
City of Mountain View
Document Title
North Bayshore Master Plan Project
Document Type
NOD - Notice of Determination
Received
Posted
6/15/2023
Document Description
The purpose of the proposed Master Plan is to implement the General Plan and Precise Plan vision for North Bayshore as a vibrant mixed-use district with new residential neighborhoods, open spaces, and mobility options. The proposed Master Plan is largely consistent with the development assumptions in the Precise Plan and certified 2017 Subsequent EIR for the North Bayshore Precise Plan (Residential Uses) (SCH# 2013082088) (2017 EIR) and would allow for the demolition of 68 of the existing 69 buildings (as well as removal of related surface parking lots and landscaping) to construct: • Up to 7,000 residential dwelling units (including 15 percent affordable residential units); • Up to 3,145,897 million square feet of office space (including 1,303,250 square feet of net new office space and 1,842,647 square feet of existing office space to be redeveloped); • 14.8 acres of public open space and 11.3 acres of Privately Owned Publicly Accessible (POPA) open space; • Up to 244,000 square feet of retail uses; • Up to of 55,000 square feet of community facilities; • Up to 525 hotel rooms; • A 2,000 square foot Police Operations Station; • Up to six above-ground parking structures; and • As an option, a private district utility system with an approximately 130,000 square-foot District Central Plant DCP and underground distribution/collection lines to serve the buildings within the Master Plan with wastewater, recycled water, thermal energy (heating and cooling), electric power via a microgrid, and/or pneumatic waste collection. Implementation of the Master Plan would require the removal of existing trees, including Heritage Trees. The proposed project would plant replacement trees in conformance with the City requirements. The maximum building heights would range from approximately 45 to 160 feet (with certain building elements to exceed the maximum specified height in the Precise Plan, per a variance application). The project would also include back-up power systems to facilitate fire and life safety loads in an emergency, in addition to diesel-powered emergency generators at each building. Parking within the Master Plan area would be provided in surface, podium, and/or below ground parking facilities, as well as within three additional district parking garages. One of the district parking garages is proposed to be constructed on the City-owned Lot C (APN 116-20-043). The Master Plan includes a Vesting Tentative Map and a Development Agreement to vest the Master Plan’s development rights over a 30-year period. The primary components of the Master Plan include the following: • Master Plan Subareas • Parks and Open Space • Utilities (including an option for private district utility systems) • Emergency Generators • Green Building and Emissions Reduction Features • Construction Activities and Phasing • Site Access, Circulation, and Parking • Transportation Demand Management • Heritage Trees and Landscaping Aspects of the proposed Master Plan not included within the adopted Precise Plan and/or evaluated in the certified 2017 EIR are the construction and operation of: • One proposed above ground parking garage outside of the Precise Plan area (APN: 116-20-043) • 325 additional hotel rooms • 199,206 additional square feet of retail space • 66,957 additional square feet of institutional/recreational space

Contact Information

Name
Diana Pancholi
Agency Name
City of Mountain View
Job Title
Principal Planner
Contact Types
Lead/Public Agency

Location

Cities
Mountain View
Counties
Santa Clara
Regions
Citywide, Countywide, San Francisco Bay Area
Cross Streets
Shoreline Blvd/Space Park Way, Shoreline Blvd/Plymouth St, Huff Ave/Charleston Rd, Shoreline Blv
Zip
94043
Total Acres
153
Parcel #
116-10-108, 116-10-107, 116-10-105, 116-10-104, 116-10-102, 116-10-101, 116-10-111, 116-10-095,
State Highways
SR 85, SR 82, SR 237
Railways
Caltrain, VTA light rail
Airports
Moffett Federal Airfield
Schools
Crittenden, Monta Loma, Stevenson
Waterways
Stevens Creek, Permanente Creek, Adobe Creek, Barron Creek
Township
6S
Range
2W
Section
10

Notice of Determination

Approving Agency
City of Mountain View City Council
Approving Agency Role
Lead Agency
Approved On
County Clerk
Santa Clara
Final Environmental Document Available at
City of Mountain View Planning Division. 500 Castro Street, Mountain View, CA 94041

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print