Temporary Easement for the Interstate 80/Richards Boulevard Interchange Improvements Project
3 Documents in Project
Summary
SCH Number
2022020587
Lead Agency
City of Davis
Document Title
Temporary Easement for the Interstate 80/Richards Boulevard Interchange Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
3/8/2023
Document Description
The City of Davis, in cooperation with the California Department of Transportation (Caltrans), proposes to reconstruct the westbound ramps at the I-80/Richards Boulevard interchange in the City of Davis by converting from a cloverleaf to a tight diamond configuration, construct a grade-separated bicycle and pedestrian path along the west side of Richards Boulevard, close the isolated westbound off-ramp to Olive Drive, and make other related improvements. The University’s approval in association with the Project is limited to the granting of a temporary construction easement to allow for the construction of the Project. The easement would allow the City access to 5,129 square feet of land at 1441 and 1333 Research Drive, Davis, CA 95616 for 24 months. Landscaping within the proposed easement area will be protected in place or restored by the project contractor after construction.
Contact Information
Name
Brian Harrington
Agency Name
University of California
Job Title
Director of Physical and Environmental Planning
Contact Types
Responsible Agency
Phone
Location
Cities
Davis
Counties
Yolo
Regions
Northern California
Other Location Info
Richards Boulevard and Interstate 80
Notice of Determination
Approving Agency
University of California
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Yolo
Final Environmental Document Available at
City of Davis, 23 Russell Boulevard, Davis, CA 95616 and https://www.cityofdavis.org/city-hall/improvement-projects/richards-boulevard-i-80-interchange-improvements
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.