Willow Distribution Station Upgrades Project

2 Documents in Project

Summary

SCH Number
2022020502
Lead Agency
Burbank Water and Power
Document Title
Willow Distribution Station Upgrades Project
Document Type
NOD - Notice of Determination
Received
Posted
4/26/2022
Document Description
The project involves the demolition of the existing Naomi Distribution Station which is currently owned and operated by Burbank Water and Power as a 34.5/4.3 kilovolt (kV) distribution station and will be re-constructed as a new 69/12.47kV station. New underground 69kV and 12.47kV conduits and duct banks (proposed and future) carrying new high voltage power cables and fiber optic cables would be installed from inside the substation to go across both South Naomi Street and West Willow Street in the public right-of-way past the property line. The underground transmission cables would also be installed in public right-of-way in the following roadways: North and South Frederic Street, West Olive Avenue, West Verdugo Avenue, North California Street, and West Alameda Avenue. Construction activities are anticipated to take up to 24 months. Construction of the proposed project includes demolition, trenching, grading and installation of electric utility infrastructure, landscape improvements, and paving.

Contact Information

Name
Michael Wang
Agency Name
Burbank Water and Power
Job Title
Senior Electrical Engineer
Contact Types
Lead/Public Agency

Location

Cities
Burbank
Counties
Los Angeles
Regions
Citywide
Cross Streets
S. Naomi Street / W. Willow Street
Zip
91502
Total Acres
0.39
Parcel #
2484-021-900
State Highways
SR-134, I-5
Railways
Metrolink
Schools
Multiple
Waterways
Los Angeles River

Notice of Determination

Approving Agency
City of Burbank
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
City of Burbank, Burbank Water & Power office: 164 W. Magnolia Boulevard , Burbank, CA 91502

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.