Poplar at Golf Course Trash Capture Project

2 Documents in Project

Summary

SCH Number
2022010369
Lead Agency
City of San Mateo
Document Title
Poplar at Golf Course Trash Capture Project
Document Type
NOD - Notice of Determination
Received
Posted
3/25/2022
Document Description
The project would involve installation of a full trash capture device that is approved by the State Water Resources Control Board within a concrete lined drainage channel at the location immediately north of the intersection of East Poplar Avenue and North Bayshore Boulevard. The trash capture device would include four screens which would be prefabricated, would be installed at two-foot intervals along a three-foot high by one-foot wide concrete weir wall, and would be secured with stainless steel anchor plates. The project would also provide native vegetation enhancement along Poplar Creek within the Poplar Creek Golf Course to offset project impacts to the Poplar Creek. The project would enhance approximately 1,000 square feet (0.02 acre) of stream. Temporary irrigation would be installed, and a monitoring program would be instituted to ensure that the plantings for enhancement establish.

Contact Information

Name
Elton Yee
Agency Name
City of San Mateo
Job Title
Associate Engineer
Contact Types
Lead/Public Agency / Project Applicant

Location

Cities
San Mateo
Counties
San Mateo
Regions
Citywide
Cross Streets
East Poplar Avenue and North Bayshore Boulevard.
Waterways
Poplar Creek

Notice of Determination

Approving Agency
City of San Mateo
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Mateo
Final Environmental Document Available at
https://www.cityofsanmateo.org/DocumentCenter

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.