Blackwell’s Corner CAPM Project (California Endangered Species Act Incidental Take Permit No. 2081-2023-029-04 (ITP), Amendment No. 1)
8 Documents in Project
Summary
SCH Number
2022010218
Lead Agency
California Department of Transportation, District 6
(DOT)
Document Title
Blackwell’s Corner CAPM Project (California Endangered Species Act Incidental Take Permit No. 2081-2023-029-04 (ITP), Amendment No. 1)
Document Type
NOD - Notice of Determination
Received
Posted
10/14/2024
Document Description
The Project includes repaving SR 33 between PMs 40.4 and 59.3, adding 4-foot-wide paved shoulders along both sides of the highway in areas where the shoulder does not exist or is narrower than 4 feet, and extending, replacing, or repairing 19 culvert facilities within this section. Project work is anticipated to start in winter 2023 and be completed by fall 2024. The start date may be delayed by winter weather until spring 2024. Caltrans anticipates a total of 200 working days, which includes 60 nights.
The Project will result in 10.242 acres of temporary and 55.11 acres of permanent impacts to San Joaquin antelope squirrel (Ammospermophilus nelsoni) and San Joaquin kit fox (Vulpes macrotis mutica) habitat. The project is expected to result in incidental take of San Joaquin antelope squirrel and San Joaquin kit fox, which are both designated as threatened species under the California Endangered Species Act. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation. Amendment No. 1 authorizes extensions of the permit expiration date and compensatory mitigation requirement date, and changes to project impacts and some Conditions of Approval. Issuance of this Amendment does not increase the amount of take of the Covered Species compared to the Project as originally approved or otherwise increase other Project impacts on the Covered Species.
Contact Information
Name
Adam Thompson
Agency Name
CDFW
Job Title
Senior Environmental Scientist Specialist
Contact Types
Responsible Agency
Phone
Location
Counties
Kern
Regions
Southern California
State Highways
SR 33
Other Location Info
The Blackwell’s Corner CAPM Project (Project) is located on State Route (SR) 33 between postmiles 40.4 and 59.3, approximately 6.6 miles northwest of McKittrick, north to Blackwell’s Corner, within Kern County.
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.