Document Description
The project proposes to extend the existing boat ramp 8 ft. and widen the ramp from 6 in. at seawall to 14 ft. at the lakeward extent. Tules are NOT present in the project area and will not be impacted by the proposed project. Work in the lake will likely occur between October 15 and December 31, but may occur outside of the work window. The project will further require a lakebed encroachment permit from Lake County Water Resources Department and a building permit from the Building Department. A vicinity map is attached.

Contact Information

Name
Tracy Cline
Agency Name
County of Lake, Community Development Department
Job Title
Associate Resource Planner
Contact Types
Lead/Public Agency

Location

Cities
Kelseyville
Counties
Lake
Regions
Countywide
Parcel #
044-101-10

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
Class 3 New Construction - 15303 (e)
Reasons for Exemption
Class 3 – New Construction. The project proposes to extend the existing boat ramp 8 ft. and widen the ramp from 6 in. at seawall to 14 ft. at the lakeward extent. The lakebed is currently dry due to drought conditions and the work will not impact water quality. No littoral vegetation will be removed. All work in the lake will occur between October 15 and December 31. The project will not result in significant adverse environmental effects to wetlands or riparian habitats. The Lake County Community Development Department has determined that the project will not have a significant effect on the environment and is, therefore, exempt from the provisions of CEQA.

Exempt Status
Categorical Exemption
Type, Section or Code
Class 1 Existing Facilities - 15301 (d)
Reasons for Exemption
Class 1 – Existing Facilities. The project proposes to repair and extend an existing boat ramp. Class 3 – New Construction. The project proposes to extend the existing boat ramp 8 ft. and widen the ramp from 6 in. at seawall to 14 ft. at the lakeward extent. The lakebed is currently dry due to drought conditions and the work will not impact water quality. No littoral vegetation will be removed. All work in the lake will occur between October 15 and December 31. The project will not result in significant adverse environmental effects to wetlands or riparian habitats. The Lake County Community Development Department has determined that the project will not have a significant effect on the environment and is, therefore, exempt from the provisions of CEQA.
County Clerk
Lake

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.