PLNP2021-00011 SLOUGHHOUSE SOLAR FACILITY

6 Documents in Project

Summary

SCH Number
2021100444
Lead Agency
Sacramento County
Document Title
PLNP2021-00011 SLOUGHHOUSE SOLAR FACILITY
Document Type
NOD - Notice of Determination
Received
Posted
1/10/2024
Document Description
The project will construct, operate, and decommission a new 50-megawatt (MW) solar energy facility on an approximately 381-acre project site in the Cosumnes community of unincorporated Sacramento County. The project will result in the construction, operation, and eventual decommissioning of solar-energy generation, energy storage, and electrical distribution facilities. The project parcels would be developed with solar panel arrays and ancillary facilities, energy storage facilities, an electrical substation, internal roads, retention basins, and distribution lines connecting to the regional power grid. The project is located on agricultural grazing lands and is adjacent to an existing solar energy facility. The electrical power provided by the project would be supplied to the Sacramento Municipal Utility District (SMUD) using existing, adjacent SMUD distribution facilities.

Contact Information

Name
Julie Newton
Agency Name
Sacramento County Planning
Job Title
ENVIRONMENTAL COORDINATOR
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Regions
Countywide
Parcel #
126-0110-001 and 126-0110-003

Notice of Determination

Approving Agency
Sacramento County Planning
Approving Agency Role
Lead Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
https://planningdocuments.saccounty.net/

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print