Big Tujunga Reservoir Restoration Project

2 Documents in Project

Summary

SCH Number
2021090475
Lead Agency
Los Angeles County Department of Public Works (DPW)
Document Title
Big Tujunga Reservoir Restoration Project
Document Type
NOD - Notice of Determination
Received
Posted
1/17/2023
Document Description
The Project involves removal of between 2.1 mcy and 4.4 mcy of sediment from BTR and depositing the sediment in Maple Canyon SPS. The purpose of the Project is to maintain the capacity of the reservoir and protect the operability of the outlet works, which are necessary to protect life and property by attenuating storm water flow peaks and to capture locally generated water to support the region’s water supply. Other minor activities include: hydroblasting to flush a stilling well on the dam crest; repair of the hydraulic sluicegate; access road paving and repair of the culvert crossing; slope protection measures adjacent to the spillway; rehabilitating the northern access ramp to safely access the reservoir bottom; installing a boat dock at the dam face; and performing minor coring on existing dam riser and installing a slide gate to facilitate dewatering.

Contact Information

Name
George De La O
Agency Name
Los Angeles County Flood Control District
Job Title
Senior Civil Engineer
Contact Types
Lead/Public Agency

Location

Counties
Los Angeles
Regions
Countywide
Cross Streets
Big Tujunga Canyon Road/Angeles Forest Highway
Zip
91501
Total Acres
45
State Highways
State Route 2
Railways
None
Airports
None
Schools
None
Waterways
Big Tujunga Canyon Creek
Township
2N
Range
13W
Section
1
Base
C Peak

Notice of Determination

Approving Agency
Los Angeles County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
900 South Fremont Avenue, 2nd Floor, Alhambra, California 91803

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print