West Coast Waste Co., Inc. Fresno Renewable Energy Station
2 Documents in Project
Summary
SCH Number
2021080094
Lead Agency
City of Fresno
Document Title
West Coast Waste Co., Inc. Fresno Renewable Energy Station
Document Type
NOD - Notice of Determination
Received
Posted
9/30/2021
Document Description
Notice of Determination for Conditional Use Permit (CUP) Application No. P18-03189 proposes to amend the prior CUP No. 15-030 by adding a Biomass Cogeneration Plant (BCP), and a wood pellet mill to the existing West Coast Waste Material Recovery Facility (MRF)
Currently the MRF accepts 1,500 TPD of clean (pre-sorted) and green organic materials, wood waste, and wood chipping suitable for recycled use by others. Some of this material cannot be recycled and must be disposed at a local landfill. The Project will divert a maximum of 200 TPD of this waste organic and wood material from disposal at a local landfill and will instead be utilized as feedstock in the new BCP. This BCP will generate renewable electricity via a fully enclosed gasification/combustion process to create steam to run a turbine generator. The turbine will generate approximately five (5) MW, of which 1.2 to 2.0 megawatts (MW) will be used to offset grid power used by the new process and to power new electric grinders. The remaining 3 MW will be sold to PG&E through an interconnection at the north edge of the site on South Golden State Frontage Road.
Contact Information
Name
Jose Valenzuela
Agency Name
City of Fresno
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Fresno
Counties
Fresno
Cross Streets
southside of East North Avenue, between South Cedar Avenue and South Golden State Boulevard
Zip
93725
Total Acres
2.1 acres
Parcel #
330-060-49S & -42
State Highways
99
Railways
Union Pacific & BNSF
Notice of Determination
Approving Agency
City of Fresno
Approving Agency Role
Lead Agency
Approved On
County Clerk
Fresno
Final Environmental Document Available at
City of Fresno, 2600 Fresno Street, Fresno, CA 93726
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.