PSP 20-068 (Tulare 40 Generation Facility Project)

2 Documents in Project

Summary

SCH Number
2021040778
Lead Agency
Tulare County
Document Title
PSP 20-068 (Tulare 40 Generation Facility Project)
Document Type
NOD - Notice of Determination
Received
Posted
7/30/2021
Document Description
Project Description: The Project includes the construction and operation of the Tulare 40 Generation Facility (Project), an approximate 40-megawatt (MW) solar generation facility. The installation would comprise approximately 129,000 fixed axis mounted solar modules, rated at 410 watts per module. It should be noted that watts per module may increase at time of Project construction; however, for planning purposes we have included an approximate module output of 410 watts. In addition to the installation of photovoltaic (PV) solar modules, both the north and south proposed development areas of the proposed Project would include the construction of an on-site substation, wiring and inverters, fence, access roads, and a new distribution interconnect power line (on existing poles) along public road rights of way to the existing substation located approximately 5.4 linear miles southeast of the Project location at the Southern California Edison (SCE) Bliss Substation. The southern proposed development areas of the Project would potentially include a 5 megawatt-hour (MWhr) storage component in the form of batteries.

Contact Information

Name
Hector Guerral
Agency Name
Tulare County Resource Management Agency
Contact Types
Lead/Public Agency

Location

Counties
Tulare
Parcel #
195-070-025, 195-060-041, 195-060-050
Township
20S
Range
25 E
Other Location Info
Section: 2, 11, 12
Other Information
Addressed 23599 Rd 152 and 22996 Rd 152. Located approximately 5 miles east of the City of Tulare and is east of Road 152.

Notice of Determination

Approving Agency
Tulare County Resource Management Agency
Approving Agency Role
Lead Agency
Approved On
County Clerk
Tulare
Final Environmental Document Available at
Tulare County Resource Management Agency, 5961 S Mooney Blvd., Visalia, CA

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.