Tassajara Pipeline Project

3 Documents in Project

Summary

SCH Number
2021040034
Lead Agency
Dublin San Ramon Services District
Document Title
Tassajara Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
6/4/2021
Document Description
DSRSD proposes to install approximately 1,110 linear feet of 8-inch-diameter high-density polyethylene (HDPE) pipeline to connect an existing 10-inch-diameter pipeline within an unpaved extension of Cydonia Court with an existing 8-inch-diameter pipeline within Delamar Drive in the Tassajara Hills Development in the City of Dublin. Approximately 800 feet of the proposed pipeline would be installed using horizontal directional drilling, whereby a tunnel is drilled under the ground surface and the pipeline is then pulled through the underground tunnel. The remaining 300 linear feet of pipeline would be installed using standard open trench construction within existing graded areas associated with adjacent residential development. The proposed pipeline would provide a redundant potable water supply to the Tassajara Hills Development.

Contact Information

Name
Jackie Yee
Agency Name
Dublin San Ramon Services District
Contact Types
Lead/Public Agency / Parties Undertaking Project

Location

Cities
Dublin
Counties
Alameda
Regions
San Francisco Bay Area
Cross Streets
Delamar Drive, Cydonia Court
Zip
94568
Total Acres
3.79
Parcel #
985-0028-003-02 and 985-127-002-00
Township
2S
Range
1E
Section
22, 27
Base
Livermor

Notice of Determination

Approving Agency
Dublin San Ramon Services District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Alameda
Final Environmental Document Available at
Dublin San Ramon Services District website: https://www.dsrsd.com/about-us/news

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print