North City Landfill Closure Project

2 Documents in Project

Summary

SCH Number
2021010226
Lead Agency
Sacramento Municipal Utility District
Document Title
North City Landfill Closure Project
Document Type
NOD - Notice of Determination
Received
Posted
5/27/2021
Document Description
The North City Landfill Closure Project is a landfill closure project of two properties (North City Landfill property and Lot 31) with historic landfill activities, in compliance with California Department of Resources Recycling and Recovery requirements and the California Code of Regulations Title 27 solid waste regulations, as regulated by Sacramento County Environmental Management Department as the Local Enforcement Agency in Sacramento County. The project would include demolition of concrete slab and piers, grading the site for proper drainage, importing soil for the soil cover, constructing a gravel maintenance road, transmission tower maintenance pads and the final soil cover, and developing site drainage improvements and erosion control. Upon completion of landfill closure activities, a post-remediation site monitoring and maintenance plan would be implemented as part of the project to address issues such as site inspections, environmental monitoring, cover maintenance, utility construction, and maintenance of existing and future utilities.

Contact Information

Name
Kim Crawford
Agency Name
Sacramento Municipal Utility District
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Regions
Citywide
Total Acres
12 acres
Airports
N/A

Notice of Determination

Approving Agency
Sacramento Municipal Utility District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
www.SMUD/ceqa

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.