Addendum to Innovative Barracuda Chassis Depot Final IS/ND

3 Documents in Project

Summary

SCH Number
2020080336
Lead Agency
Port of Los Angeles
Document Title
Addendum to Innovative Barracuda Chassis Depot Final IS/ND
Document Type
NOD - Notice of Determination
Received
Posted
3/15/2021
Document Description
The proposed Project would entitle property currently operated as a chassis depot to include the new use of cargo handling support, which adds the storage and handling of shipping containers for the entire premises. The new activities would operate in conjunction with the chassis depot operations evaluated in the Final IS/ND. Additionally, an approximately 2.65 acre expansion would be added for existing truck trip queuing and as-needed storage on Barracuda and Bass Streets, which are currently closed off from thoroughfare, expanding the entitled area to approximately 16.40 acres. These street entitlements would be terminated when street access needs to be restored. Also, a minor construction component would be added, which is grading and laying of crushed aggregate base or gravel for the duration of a short-term entitlement. This entitlement would not exceed 12 months and includes incorporation of Best Management Practices. The facility is part of Port property located on the western portion of Terminal Island. The proposed modifications would create no potential adverse impacts or substantial changes to impact areas previously analyzed in the Final IS/ND.

Contact Information

Name
Leah Kohler
Agency Name
City of Los Angeles- Port of Los Angeles (Harbor Department)
Contact Types
Lead/Public Agency

Location

Cities
San Pedro
Counties
Los Angeles
Regions
Citywide
Other Information
915 Earle Street, San Pedro, CA 90731

Notice of Determination

Approving Agency
City of Los Angeles- Port of Los Angeles (Harbor Department)
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
https://www.portoflosangeles.org/environment/environmental-documents

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print