Upper Drainages Erosion Control Improvements

4 Documents in Project

Summary

SCH Number
2020060620
Lead Agency
California Department of Transportation, District 5 (DOT)
Document Title
Upper Drainages Erosion Control Improvements
Document Type
NOD - Notice of Determination
Received
Posted
12/16/2020
Present Land Use
state highway
Document Description
The project would replace or modify drainage systems that are deteriorated and/or undersized and that are plugging, overtopping, or flooding and thereby causing erosion. The project would plug and fill the old pipe culverts; install new, larger pipe culverts; place rock slope protection at outlets where needed; replace substandard inlets; and add minor paving where open ground is causing excessive sediment in the drainage system. An existing retaining wall would be rebuilt and lengthened. The Skyline-to-the-Sea Trail would be repaired where erosion has created a slipout. Guardrail would be repaired where necessary.

Contact Information

Name
Paula Huddleston
Agency Name
California Department of Transportation
Contact Types
Lead/Public Agency

Location

Counties
San Mateo, Santa Cruz
Regions
Countywide, Northern California, Unincorporated
Cross Streets
multiple
State Highways
Route 9
Railways
none
Airports
none
Schools
none
Waterways
San Lorenzo River and tributaries
Other Location Info
Near Ben Lomond and Boulder Creek
Other Information
Along Highway 9 in Santa Cruz and San Mateo Counties from Scenic Way in Ben Lomond to 0.25 mile north of the Summit Meadows trailhead parking lot.

Notice of Determination

Approving Agency
California Dept of Transporation
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print