MEASURE RR PROGRAM TRACTION POWER SYSTEM IMPROVEMENT PROGRAM

Summary

SCH Number
2020060466
Public Agency
Bay Area Rapid Transit District (BART)
Document Title
MEASURE RR PROGRAM TRACTION POWER SYSTEM IMPROVEMENT PROGRAM
Document Type
NOE - Notice of Exemption
Received
Posted
6/22/2020
Document Description
The San Francisco Bay Area Rapid Transit District (BART) is an electricity powered commuter transit line. Electrification is provided by "traction power" substations located along the transit line right-of-way. BART proposes improvements to one of its existing traction power substations, Downtown Berkeley Station BART Substation, referred herein as "RBE". RBE is located at the mezzanine level of the Downtown Berkeley BART station (2160 Shattuck Avenue, Berkeley, CA 94704), one level below the street level. The project will require facility upgrades, procurement, and Installation of replacement equipment for the existing traction power substation which currently supplies power for BART rail operations.

Contact Information

Name
Steve Sims
Agency Name
San Francisco Bay Area Rapid Transit District
Contact Types
Lead/Public Agency

Name
Agency Name
Steve Sims
Contact Types
Project Applicant

Location

Cities
Berkeley
Counties
Alameda

Notice of Exemption

Exempt Status
Statutory Exemption
Type, Section or Code
15275(a)
Reasons for Exemption
The proposed replacement of the traction power substation equipment qualifies for a statutory exemption from CEQA, as the project fits into the context of the exemption language and no other significant effects on the environment will result due to unusual circumstances. Statutory exemptions from CEQA are granted by legislature. A statutory exemption is provided under Section 21080(b)(10) of the California Public Resources Code (also found in the CEQA Guidelines Article 18 Section 15275(a)). This statutory exemption applies to mass transit projects that involve the institution or increase of passenger or commuter service on rail lines already in use. This project proposes removing aging train control equipment and upgrading to a new system, which will support increased capacity and higher service frequencies.

Attachments

Notice of Exemption

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.