Document Title
PP1 Bank Stabilization Project
Document Type
NOE - Notice of Exemption
Received
Posted
6/5/2020
Document Description
The Los Angeles Department of Water and Power (LADWP) proposes to install riprap reinforcement along a portion of Clearwater Creek near LADWP's PP1 facility. Approximately 615 cubic yards of riprap would be placed at a 2:1 (H:V) slope along approximately 205' of the creek bank. The stream bank is roughly 10' in height and riprap would be placed up to 18' into the stream. This bank along this portion of Clearwater Creek has been compromised by erosions caused partially by native tree roots and threatens to weaken the integrity of the abutting access road which is used as the primary road to PP1. This causes concern for any super-heavy equipment needed to access PP1 for plant maintenance.

Contact Information

Name
Aiden Leong
Agency Name
Los Angeles Department of Water and Power (LADWP)
Contact Types
Lead/Public Agency

Location

Cities
Santa Clarita
Counties
Los Angeles
Other Location Info
The project site is located along Clear Creek Road, approximately 300 feet south of Power Plant No. 1 (PP1), in Santa Clarita, CA. Power Plant 1 facility is located off of San Francisquito Canyon Road, approximately 4 miles south of Green Valley, California and approximately 18 miles north of the City of Santa Clarita, California.

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
CEQA Guidelines Section 15301 Existing Facilities – Class 1
Reasons for Exemption
In accordance with the California Environmental Quality Act (CEQA), it has been determined that the proposed project is categorically exempt pursuant to the CEQA Guidelines Section 15301, Class 1, Existing Facilities. Class 1 consists of the maintenance and minor alteration of existing private and public structures, facilities, and topographical features, involving negligible or no expansion of use beyond that existing at the time of the lead agency’s determination. This includes existing facilities of publicly-owned utilities used to provide electric power. The proposed project would not result in the expansion of the existing capacity and extent of existing flood control infrastructure located at the Power Plant 1 facility.

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print