Three Lake Bridges Project

4 Documents in Project

Summary

SCH Number
2020049046
Lead Agency
California Department of Transportation, District 3 (DOT)
Document Title
Three Lake Bridges Project
Document Type
NOD - Notice of Determination
Received
Posted
6/15/2021
Document Description
The Project is limited to upgrading the bridge rails and shoulder widths at the Morrison Creek and Robinson Creek Bridges, and to replace the bridge at Kelsey Creek in order to support the shoulder widening and new rails. The Project will also involve channel grading, the removal of sediment and rock slope protection, installation of piers and footings, installation of a retaining wall, and the installation and replacement of a culvert adjacent to the bridge locations. The Project will bring all three bridges to current structural design standards.

Contact Information

Name
Ian Boyd
Agency Name
Department of Fish and Wildlife
Contact Types
Responsible Agency

Location

Counties
Lake
Regions
Northern California
Other Location Info
The three projects are located along State Routes (SR) 20, 29, and 175 in Lake County on Morrison Creek, Robinson Creek, Kelsey Creek, respectively. The project at Morrison Creek Bridge is located at LAK-20 post mile (PM) 16.81 with latitude 39.095878 and longitude -122.801446. The project at Robinson Creek Bridge is located at LAK-29 PM 50.82 with latitude 39.140620 and longitude -122.912462. The project at Kelsey Creek Bridge is located at LAK-175 PM 19.48 with latitude 39.823987 and longitude -122.721397.

Notice of Determination

Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Lake
Final Environmental Document Available at
the office location listed above for the Lead Agency. CDFW’s record of execution of the Streambed Alteration Agreement as Responsible Agency is available at CDFW’s regional office.

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.