Concurrence with the issuance of a New Solid Waste Facilities Permit for Agromin Limoneira Commercial Organics Processing Operations, Ventura County, 56-AA-0179

4 Documents in Project

Summary

SCH Number
2020039054
Lead Agency
Ventura County
Document Title
Concurrence with the issuance of a New Solid Waste Facilities Permit for Agromin Limoneira Commercial Organics Processing Operations, Ventura County, 56-AA-0179
Document Type
NOD - Notice of Determination
Received
Posted
11/3/2022
Document Description
Project includes the following: Proposed transfer/processing facility, composting facility and in-vessel digestion facility; hours of operation for receipt of waste, maintenance, and office will be 7:00am-5:00pm and 6:00am-6:00pm during peak season; hours of operation for material processing/packaging will be 6:00am-4:00pm and 6:00am-6:00pm during peak season; hours of operation for outdoor processing will be sunrise to sunset; hours of operation for in-vessel digestion/maintenance will be 24 hours per day, 7 days per week; permitted maximum tonnage will be 1,250 tons per day; permitted traffic volume will be 385 vehicles per day; total permitted area will be 70 acres; and the design capacity will be 1,250 tons per day.

Contact Information

Name
Theodore Tasiopoulos
Agency Name
CalRecycle
Job Title
Environmental Scientist
Contact Types
Responsible Agency

Name
John Oquendo
Agency Name
Ventura County
Job Title
Planner
Contact Types
Lead/Public Agency

Name
Bill Camarillo
Agency Name
Agromin
Job Title
Operator
Contact Types
Project Applicant

Location

Cities
Santa Paula
Counties
Ventura
Regions
Southern California
Other Location Info
South Terminus of Edwards Ranch Road

Notice of Determination

Approving Agency
CalRecycle
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Ventura
Final Environmental Document Available at
https://ceqanet.opr.ca.gov/2020039054/3

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
No