Conveyance of 2020 Water Transfer from El Dorado Irrigation District to Westlands Water District (SWPAO #20753)

3 Documents in Project

Summary

SCH Number
2020039045
Lead Agency
El Dorado Irrigation District
Document Title
Conveyance of 2020 Water Transfer from El Dorado Irrigation District to Westlands Water District (SWPAO #20753)
Document Type
NOD - Notice of Determination
Received
Posted
9/30/2020
Document Description
PROJECT DESCRIPTION El Dorado Irrigation District (District) has requested that DWR convey up to 8,421 acre-feet of transfer water to Westlands made available by additional releases from Caples Lake and Silver Lake that otherwise would be added to storage in Jenkinson Lake. The District also has a separate conveyance agreement (SWPAO #20-752) with DWR and Westlands regarding the transfer of stored releases from Weber Reservoir. The combined maximum transfer amount from Caples Lake, Silver Lake, and Weber Reservoir will be 8,421 acre-feet. The point of transfer will be Folsom Lake Reservoir. The transfer water will flow to the Sacramento-San Joaquin Delta, where DWR will export the transfer water through the SWP Banks Pumping Plant and convey it to Westlands’ service area through the California Aqueduct.

Contact Information

Name
Brian Heiland
Agency Name
Department of Water Resources
Contact Types
Lead/Public Agency

Location

Counties
El Dorado
Other Location Info
El Dorado County and the service area of Westlands Water District (Westlands). The Project will use existing State Water Project (SWP) facilities.

Notice of Determination

Approving Agency
DWR
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.