Doty North Canal Siphon #1 Replacement Project
2 Documents in Project
Summary
SCH Number
2020029068
Lead Agency
Nevada Irrigation District
Document Title
Doty North Canal Siphon #1 Replacement Project
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
Zoning: AG General Plan: RR 1-10 acre minimum
Document Description
The Doty North Canal Siphon #1 Replacement Project is located northwest of the Gold Hill Gardens Event Center at 2325 Gold Hill Road, Newcastle, in the foothills of western Placer County. The Project is proposed by the Nevada Irrigation District (NID) and involves replacement of an existing raw water transmission siphon that is in poor condition and has reached the end of its useful life. As part of the Project, the existing 24-inch raw water siphon crossing over Doty Ravine and Sailors Ravine would be removed and replaced with a new 350-foot long, 36-inch-diameter welded steel inverted siphon pipe. The new pipe would convey Doty Ravine North Canal raw water across Doty and Sailors Ravine consistent with the District's approved masterplan design flow rate of 34 cubic feet per second (cfs). System demands and operational constraints limit when the existing Siphon can be taken offline for replacement. This requires that construction occur during winter when water demands are lowest. As such, construction is currently planned to begin on or about October 15, 2020. Due to the flashy nature of the Doty Ravine Watershed and expected high flows during winter months, a temporary construction crossing at the Project site is not considered feasible. Primary construction access would be from the south following the existing Gold Hill Gardens paved driveway entrance off Gold Hill Road. North side construction access would be provided by a temporary easement extending approximately 1,300 feet southwesterly from Gold Hill Road. The northern access route includes a temporary crossing of Sailors Ravine and would extend through irrigated pasture and then follow an NID service road to the north side of Sailors Ravine and the Project site. Project construction is expected to take approximately six weeks and is scheduled to begin on or about October 15, 2020, or later depending on funding availability.
Contact Information
Name
Doug Roderick
Agency Name
Nevada Irrigation District
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Nevada Irrigation District
Contact Types
Project Applicant
Location
Cities
Newcastle
Counties
Placer
Cross Streets
Gold Hill Road, Schindler Road
Zip
95658
State Highways
193
Waterways
Doty Ravine, Sailors Ravine, Lincoln Canal
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Conservation (DOC), California Department of Fish and Wildlife, North Central Region 2 (CDFW), California Department of Forestry and Fire Protection (CAL FIRE), California Department of Parks and Recreation, California Department of Transportation, District 3 (DOT), California Department of Water Resources (DWR), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB), California State Lands Commission (SLC), Central Valley Flood Protection Board, Office of Historic Preservation, State Water Resources Control Board, Division of Water Quality, State Water Resources Control Board, Division of Water Rights
Project Issues
Agriculture and Forestry Resources, Biological Resources, Cultural Resources, Geology/Soils, Transportation, Wetland/Riparian
Attachments
Environmental Document
NOC
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.