Sequoia Backup Generating Facility

2 Documents in Project

Summary

SCH Number
2020010384
Lead Agency
California Energy Commission
Document Title
Sequoia Backup Generating Facility
Document Type
NOD - Notice of Determination
Received
Posted
7/1/2021
Document Description
The applicant proposes to construct and operate the project at 2600 De La Cruz Boulevard in Santa Clara, California. The project would include grading of the currently vacant site to construct a four-story 703,450 square foot data center building, electrical substation, generator equipment yard, surface parking, and landscaping. The SBGF would consist of a total of 54 diesel-fired generators that would be used exclusively to provide backup generation to support the Critical Information Technology (IT) load of the server bays, mechanical cooling loads, and house power in the event of an emergency loss of utility power supply. The maximum electrical load of the SDC would be 96.5 MW. The SDC building would house computer servers for private clients in a secure and environmentally controlled structure and would be designed to provide 67.5 MW of Critical IT power. Approximately 70,000 square feet would be dedicated for administrative and office uses. The 54 backup generators would be located in a generation yard along the west and south sides of the SDC building. Each backup generator is proposed as a fully independent package system with a dedicated and integrated fuel tank located below the bottom level of the generator. The generation yard would be electrically interconnected to the SDC building through above-ground cables to a location within the building that houses electrical distribution equipment. The SDC would include construction of a new 100 megavolt amps (MVA) electrical substation in the western portion of the site. The substation would be capable of delivering electricity to the SDC from Silicon Valley Power but would not allow any electricity generated from the SBGF to be delivered to the transmission grid.

Contact Information

Name
Leonidas Payne
Agency Name
California Energy Commission
Contact Types
Lead/Public Agency

Location

Cities
Santa Clara
Counties
Santa Clara
Regions
Northern California
Cross Streets
De La Cruz Boulevard and Martin Avenue

Notice of Determination

Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.