Site and Make-Ready Work portion of the Parnassus Research and Academic Building and West Campus Site Improvements project

11 Documents in Project

Summary

SCH Number
2020010175
Lead Agency
University of California
Document Title
Site and Make-Ready Work portion of the Parnassus Research and Academic Building and West Campus Site Improvements project
Document Type
NOD - Notice of Determination
Received
Posted
9/23/2022
Document Description
The new Parnassus Research and Academic Building (PRAB) would be constructed on the site of UC Hall. As a strategy to mitigate risk to the project schedule, the campus proposes to advance site preparation and make-ready construction elements that are not dependent upon or restrictive to the final design of the building. These site and make-ready activities include: demolition and abatement of UC Hall including exterior abatement of hazardous materials; relocation of existing data, electrical, and steam utility lines from UC Hall to maintain service to other buildings on campus; relocation of fire hydrants; and modifications to electrical service to the former Laboratory of Radiobiology building for use as the source for temporary power during construction of the PRAB; site stabilization/shoring following demolition of UC Hall; site preparation to protect the campus community from potential hazards related to construction operations including temporarily rerouting pedestrian traffic, temporary platforms for investigative equipment, and fencing; purchase of critical long-lead-time items and materials to mitigate schedule and escalation risk such as mechanical and electrical equipment, structural steel, and other raw materials.

Contact Information

Name
Brian Harrington
Agency Name
University of California
Job Title
Director of Physical and Environmental Planning
Contact Types
Lead/Public Agency

Location

Cities
San Francisco
Counties
San Francisco
Regions
San Francisco Bay Area
Other Location Info
University of California, San Francisco, Parnassus Heights campus

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.