Laurelwood Data Center Small Power Plant Exemption

2 Documents in Project

Summary

SCH Number
2019089107
Lead Agency
Energy Commission (California Energy Commission)
Document Title
Laurelwood Data Center Small Power Plant Exemption
Document Type
NOD - Notice of Determination
Received
Posted
2/5/2020
Project Applicant
MECP1 Santa Clara 1, LLC

Document Description
The applicant submitted a small power plant exemption {SPPE) application to the California Energy Commission {CEC) for the proposed Laurelwood Data Center (LDC) at 2210 Laurelwood Road in Santa Clara, California. The LDC would consist of two multi-storied data center buildings and 56 3.0-megawatt (MW) standby backup diesel-fired generators capable of providing electrical power during utility outages or certain onsite electrical equipment interruption or failure. The maximum electrical load of the LDC would be up to 99 MW, inclusive of tenant-installed information technology (IT) equipment at the LDC and cooling and ancillary electrical and telecommunications equipment operating to support IT equipment. The LDC would also include an onsite 60-kilovolt substation with an electrical supply line that would connect to a Silicon Valley Power distribution line located 0.1 mile west of the LDC. To make way for the project, demolition and removal of asphalt/foundations and underground utilities would be necessary, prior to construction. The CEC has exclusive permitting authority under the Warren-Alquist State Energy Resources Conservation and Development Act (Warren-Alquist Act) to approve or deny, applications for the construction and operation of thermal power plants that will generate SO MW or more of electricity. The SPPE process allows applicants with thermal power plants between 50 and 100 MW to obtain an exemption from the CEC's jurisdiction and proceed with local approval rather than requiring certification by the CEC.

Contact Information
Lisa Worrall
California Energy Commission
1516 Ninth Street, MS 40
Sacramento, CA 95814

Phone : (916) 654-4545

Location

Cities
Santa Clara
Counties
Santa Clara
Cross Streets
2201 Laurelwood Road

Notice of Determination

Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
CEC Docket Unit, 1516 Ninth Street Sacramento, CA 95814

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Determination
2019089107_Laurelwood Data Center Small   PDF 691 K

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print