San Gabriel Valley Water Company - El Monte (SGVWC)- San Gabriel Valley Water Company Plant B 14 Project (Project)

2 Documents in Project

Summary

SCH Number
2019079088
Lead Agency
State Water Resources Control Board
Document Title
San Gabriel Valley Water Company - El Monte (SGVWC)- San Gabriel Valley Water Company Plant B 14 Project (Project)
Document Type
NOD - Notice of Determination
Received
Posted
9/9/2019
Document Description
SGVWC proposes to construct a second reservoir at the existing Plant B14 site to allow for operational flexibility to store additional water supplied from Plant B12 during periods of low demand. The second reservoir will also allow for the existing reservoir to be taken out of service when required for routine maintenance. The existing Plant B14 facility is located within an approximately 4.02-acre site, and it currently consists of one 1.19 million gallon buried concrete reservoir, four booster pumps with a total pumping capacity of 4,000 gallons per minute, an emergency generator, and electronic control equipment.

Contact Information

Name
Shu Fang Orr
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Name
Agency Name
San Gabriel Valley Water Company
Contact Types
Project Applicant

Location

Counties
Los Angeles
Cross Streets
Intersection of Camino Del Tomasini and Valdemar Drive

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.