New Well and Pipeline Project (Parkwood CMD 19A&B Water System Improvements)

4 Documents in Project

Summary

SCH Number
2019079062
Lead Agency
Madera County
Document Title
New Well and Pipeline Project (Parkwood CMD 19A&B Water System Improvements)
Document Type
NOD - Notice of Determination
Received
Posted
8/28/2023
Document Description
The Project includes construction of a production well to replace an existing offline well on the same parcel. The new well will be capable of producing approximately 1,000 gallons per minute and includes above and below-ground associated infrastructure. New pipeline improvements would be constructed in needed areas identified by a 2016 infrastructure study. Additional improvements include two new intertie connections to the existing City of Madera water distribution system, upsizing of one section of pipe, looping, 2,200 feet of pipe at the southern end of the service area, and new water meters at all 506 service connections. The Project also includes a six-inch thick, 20 feet long by 12 feet wide, concrete slab, pumps, a fence, and a backup power generator.

Contact Information

Name
Sarah Adler
Agency Name
State Water Resources Control Board
Job Title
Environmental Scientist
Contact Types
Responsible Agency

Location

Cities
Madera
Counties
Madera
Regions
Northern California
Cross Streets
South of Avenue 13 between S Madera Avenue and Raymond Thomas Street

Notice of Determination

Approving Agency
State Water Board, Division of Financial Assistance
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Madera
Final Environmental Document Available at
State Water Board, Division of Financial Assistance 1001 I Street 16th Floor, Sacramento, CA 95814

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print