OE3 TRAINING CENTER
6 Documents in Project
Summary
SCH Number
2019029097
Lead Agency
Sacramento County
Document Title
OE3 TRAINING CENTER
Document Type
NOD - Notice of Determination
Received
Posted
12/16/2021
Document Description
The applicant is requesting a new use permit to build and operate a new campus and equipment training activities. This new use permit would replace the existing mining use permit on the subject property. The new campus and training center includes the following: 1) construction and operation of a new campus facility (without dormitory); and 2) allowance for field instruction with construction equipment on the property. The project will include the relocation of existing classrooms and equipment training from the Rancho Murieta Training Center; the dormitory and food preparation will continue to reside at the current campus location in Rancho Murieta. The field instruction area will cover 425 acres; however, only 80 acres will be actively disturbed at one time. The applicant proposes a five year rotation cycle, so that the land can rest and revegetate.
The project consists of the following Planning Entitlements:
1. A Use Permit for a private school to allow 450-acres of 1,500-acre site to be utilized as an Operating Engineers training center in the AG-80 zone.
2. A Design Review to comply with Countywide Design Guidelines.
3. A Williamson Act Contract to re-enter into contract and prevent non-renewal scheduled to occur December 2024 on portions of the subject property.
4. Williamson Act Cancellation to cancel the existing contract on the 25-acre campus site.
Contact Information
Name
Joelle Inman
Agency Name
Sacramento County Planning
Job Title
ENVIRONMENTAL COORDINATOR
Contact Types
Lead/Public Agency
Phone
Email
Location
Cities
Sacramento
Counties
Sacramento
Regions
Countywide
Parcel #
128-0090-032, 128-0110-011, and 128-0060-001
Notice of Determination
Approving Agency
Sacramento County Planning
Approving Agency Role
Lead Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
https://planningdocuments.saccounty.net/
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.