Solar Photovoltaic (PV) for the WWTP (Wastewater Treatment Plant)

3 Documents in Project

Summary

SCH Number
2019012043
Lead Agency
City of Placerville
Document Title
Solar Photovoltaic (PV) for the WWTP (Wastewater Treatment Plant)
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
municipal waste water treatment facility/public facilities/PF
Document Description
Note: Per Lead Agency, project title changed to match City's loan application - previous title: Hangtown Creek Water Reclamation Facility Clean Water State Revolving Loan Photovoltaic Facility The project consists of clearing an approx. 2.88 acre site of existing vegetation for installation of a solar pv system to provide electricity for the operation of the existing municipal waste water treatment plant. The PV system would be installed on a ground-mounted racking system on approx. 300 piers that would be driven a max of 8 ft below ground. The system would be connected to the site's 2000-amp electrical switchgear system. The PV system is estimated to achieve a 60% reduction in energy use at the plant.

Contact Information

Name
Pierre Rivas
Agency Name
City of Placerville
Contact Types
Lead/Public Agency

Location

Cities
Placerville
Counties
El Dorado
Cross Streets
2300 Cool Water Creek Rd/Mallard Lane
Zip
95667
Total Acres
2.88
Parcel #
323-210-02
State Highways
HWY 50
Schools
El Dorado HS
Waterways
Hangtown Creek
Township
10
Range
10
Section
11
Base
MDBM

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Fish and Wildlife, North Central Region 2 (CDFW), California Department of Parks and Recreation, California Department of Transportation, District 3 (DOT), California Highway Patrol, California Native American Heritage Commission (NAHC), California Public Utilities Commission (CPUC), Central Valley Flood Protection Board, Delta Protection Commission, Delta Stewardship Council, Department of Water Resources, Resources Agency, California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB), State Water Resources Control Board, Divison of Financial Assistance
State Reviewing Agency Comments
California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB), State Water Resources Control Board, Divison of Financial Assistance
Development Types
Other (Solar PV facility)
Local Actions
city CIP
Project Issues
Air Quality, Biological Resources, Cultural Resources, Geology/Soils, Noise

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.