San Diego State University Mission Valley Campus Master Plan Phase 2 Project

8 Documents in Project

Summary

SCH Number
2019011042
Lead Agency
California State University Board of Trustees
Document Title
San Diego State University Mission Valley Campus Master Plan Phase 2 Project
Document Type
NOD - Notice of Determination
Received
Posted
9/15/2021
Document Description
The San Diego Regional Water Quality Control Board issued a Clean Water Act section 401 water quality certification (Certification No. R9-2021-0174) to the Project Applicant to construct an extension of Fenton Parkway onto the 172.13-acre future Mission Valley Campus site to connect Street A for the purpose of improving multi-modal circulation for the campus. To facilitate the road extension, the existing pipe culvert will be extended approx. 100 linear feet downstream from its current terminus and a new headwall and 768-square-foot riprap dissipation pad will be constructed. Compensatory mitigation will be provided at the San Luis Rey Mitigation Bank and an on-site restoration project on Murphy Canyon Creek.

Contact Information

Name
Lisa Honma
Agency Name
RWQCB - San Diego Region
Contact Types
Responsible Agency

Name
Robert Schulz
Agency Name
San Diego State University
Contact Types
Project Applicant

Location

Cities
San Diego
Counties
San Diego
Regions
Southern California
Cross Streets
Fenton Parkway (southern terminus of), Friars Road, and Mission Village Drive
Zip
92108
Total Acres
172.13
State Highways
I-8, I-15
Railways
MTS Light Rail Line (Trolley)
Airports
Montgomery-Gibbs Executive
Waterways
San Diego River, Murphy Canyon Creek

Notice of Determination

Approving Agency
CA Regional Water Quality Control Board, San Diego Region
Approving Agency Role
Responsible Agency
Approved On
County Clerk
San Diego
Final Environmental Document Available at
The record associated with San Diego RWQCB's decision is available at 2375 Northside Drive, Ste. 100, San Diego CA 92108, ph. 619-521-1990 (Electronic File No./PIN 861764)

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print